A New 51-Kilometre Trail Connecting Orangeville to Mississauga

A major new trail project could soon create a fantastic connection between Orangeville, Caledon, Brampton and Mississauga. The project will transform the former Orangeville- Brampton Railway corridor into a multi-use recreational trail for walking, cycling and enjoying nature.

The municipalities purchased approximately 51 kilometres of the former railway corridor in 2022. The goal is to create a continuous trail that connects communities and becomes part of the wider Trans Canada Trail network.

What Will the Trail Be Like?

The trail will follow the old railway route, passing through some of the beautiful countryside and communities between Orangeville and Mississauga. Once developed, it could provide a great option for cyclists, walkers and families looking for a longer recreational route without having to travel on busy roads.

The Caledon portion is about 36 kilometres, while the entire corridor is approximately 51 kilometres. Caledon is currently working on the preliminary design, with detailed design and construction still to come.

When Will It Be Finished?

This is where things get a little complicated. There is currently no single confirmed opening date for the entire 51-kilometre trail. The project will be built in stages.

Caledon’s current plans show preliminary design taking place in 2025–2026, followed by detailed design and implementation planned over several years. The Town’s 2026 budget documents indicate implementation could continue through 2037, meaning the complete Caledon section is expected to take many years rather than opening all at once.

Mississauga is further ahead with its smaller section. The City expects to begin Phase 1 construction in fall 2026 and open that section in summer 2027.

A Trail to Look Forward To

Although it may take years before the entire Orangeville- to- Mississauga route is ready, this project is something local residents can look forward to. When completed, the trail could offer a unique way to travel between communities while enjoying the natural scenery of the region.

For now, the important thing to remember is that the full 51-kilometre trail will not be ready in 2026 or 2027. Different sections will open at different times as planning, design and construction progress.